Do substation construction and maintenance contractors need a state license in Mississippi? Working directly for the electric utility: Yes: a contractor/GC license.
Customer, developer or other non utility work: Yes: a contractor/GC license. The utility exemption here isn't settled in the statute text, so confirm with the board before relying on it.

What's different about Mississippi

  • Mississippi's storm work rules come from Miss. Code 27-113-1 to 27-113-9. Out of state businesses doing disaster work on critical infrastructure are exempt from state and local business licensing and registration, Secretary of State and Public Service Commission requirements, and most taxes.
  • Mississippi's Board of Contractors waives the electrical trade exam for contractors licensed by exam in Alabama, Louisiana, North Carolina, Ohio, South Carolina or Tennessee.
  • You need a current certificate of responsibility when you submit the bid (Miss.

Sources: Miss. Code 27-113-7 · MSBOC reciprocity information (July 2025) · Miss. Code 31-3-15 · MS electrical classifications

Substation work covers the yards where voltage is stepped up or down. What it includes and how it's licensed nationally ›

What Mississippi requires

Contractor / GC license
MSBOC Certificate of Responsibility with the Transmission/Distribution Lines classification for commercial work of $50,000+.
Directly for utility: Required   Other work: Required
Electrical contractor license
No separate license: electrical is an MSBOC classification.
Directly for utility: Not required   Other work: Not required

License quick facts Confirm with the board

Contractor / GC
License classMSBOC Certificate of Responsibility with the Transmission/Distribution Lines classification, commercial work of $50,000 and up
Fees$400 application (one classification) + $100 each added; $400 renewal
ExamYes: business and law, plus the trade exam (NASCLA accepted for some)
ExperienceQualifying party experience set by the board
RenewalEvery year
Continuing educationNone for commercial
Required insuranceGeneral liability ($300,000 per occurrence / $600,000 aggregate), workers' comp if 5+ employees, and a CPA financial statement
ApplyApply ›

Some of these figures come from secondary sources or change often, so confirm fees and timelines with the board before you apply. Sources: 30 Miss. Code R. 803-3.4 (fees); Miss. Code 31-3-14

Working directly for a power utility in Mississippi

No exemption found for contractors hired by a utility; the Transmission/Distribution Lines classification exists for this work. Confirm the threshold with MSBOC.

Official Mississippi licensing boards

How to apply in Mississippi

Commercial application $400 plus $100 per added classification; Municipal and Public Works and Heavy classifications also available

Licensed in another state? See Mississippi electrical license reciprocity.

Why licensing matters in Mississippi

When you need the license
Before you bid
Penalties for unlicensed work
You need a current certificate of responsibility when you submit the bid (Miss. Code 31-3-15).
Getting paid
Any contract issued or awarded in violation of the law is null and void (31-3-15).

Statutes:

Who hires substation crews in Mississippi

The largest electric utilities in Mississippi by customers: Entergy Mississippi LLC (460,181 customers); Mississippi Power Co (192,416 customers); Coast Electric Power Assn (90,247 customers); Singing River Elec Cooperative (80,261 customers); Southern Pine Electric Cooperative (70,771 customers); Pearl River Valley El Pwr Assn (53,958 customers). All 50 Mississippi utilities ›

Insurance for substation crews · limits by utility

TAKKEL Insurance SponsoredGet substation contractor insurance quotes in Mississippi
Coverage for substation crews working in Mississippi.
Start a quote ›

Common questions

Do I need a license to do substation work for a utility in Mississippi?
Yes. Substation work done directly for the electric utility in Mississippi requires a contractor/GC license. The utility exemption here isn't settled in the statute text, so confirm with the board before relying on it. No exemption found for contractors hired by a utility; the Transmission/Distribution Lines classification exists for this work. Confirm the threshold with MSBOC.
Do I need a license for substation work that isn't for the utility in Mississippi?
Yes. Substation work done for a customer, developer or other non utility owner in Mississippi requires a contractor/GC license.
Which board licenses substation construction and maintenance contractors in Mississippi?
In Mississippi, substation construction and maintenance contractors deal with MS State Board of Contractors for state licensing.
How long does a Mississippi electrical contractor license last?
Mississippi doesn't issue a separate electrical contractor license; electrical and line work falls under the MSBOC Certificate of Responsibility with the Transmission/Distribution Lines classification, commercial work of $50,000 and up. The Mississippi contractor license renews every year, so put the date on your calendar and renew before it lapses. Continuing education: None for commercial.
How much does a Mississippi electrical contractor license cost?
Mississippi doesn't issue a separate electrical contractor license; electrical and line work falls under the MSBOC Certificate of Responsibility with the Transmission/Distribution Lines classification, commercial work of $50,000 and up. State fees for the contractor license: $400 application (one classification) + $100 each added; $400 renewal. Bond, insurance and exam vendor fees are extra. Confirm current fees with the board before you apply.

See all 50 electric utilities in Mississippi with links to their websites.

Other Mississippi work types

Same work type in other states: Substation licensing in all 50 states and DC