Line, underground and fiber contractor licensing by state · researched November 2026

Contractor License Bonds by State

Reviewed by Michael Schaeffer · Last verified November 18, 2026

Contractor and electrical contractor license bonds for utility contractors · researched November 2026

The short answer11 states and DC require a license bond for a contractor or electrical contractor license. A few more require one only in some cases, such as low credit, no financial statement, or out of state contractors. Many states require no state license bond at all, but cities and counties can still add their own.
TAKKEL Insurance SponsoredNeed a license bond?
License, bid, performance and payment bonds for utility contractors.
Get bonded ›

License bonds in every state

"Confirm with the board" means we couldn't verify the amount against the board's own pages.

StateContractor bondElectrical bondLocal bondsGuide
AlabamaNot required
None
Not required
None
Cities and counties may add their ownGuide ›
AlaskaRequired
$25,000 general contractor; $10,000 specialty or mechanical contractor
Required
$10,000 (specialty contractor registration)
Cities and counties may add their ownGuide ›
ArizonaRequired
$5,000 to $100,000, set by your classification and estimated yearly volume
Required
$2,500 to $50,000 for commercial specialty licenses such as C-11, set by yearly volume
Cities and counties may add their ownGuide ›
ArkansasNot required
None
Not required
None
Cities and counties may add their ownGuide ›
CaliforniaRequired
$25,000 contractor bond
Required
$25,000 (same CSLB bond; C-10 is a CSLB classification)
Cities and counties may add their ownGuide ›
ColoradoSet locally
Set by cities and counties
Not required
None
Cities and counties may add their ownGuide ›
ConnecticutSet locally
Set by cities and counties
Not required
None
Cities and counties may add their ownGuide ›
DelawareOnly in some cases
6% of the contract price on contracts of $20,000 or more
Not required
None
Cities and counties may add their ownGuide ›
District of ColumbiaSet locally
Set by cities and counties
Required
Confirm with the board
Cities and counties may add their ownGuide ›
FloridaOnly in some cases
Confirm with the board
Only in some cases
Confirm with the board
Cities and counties may add their ownGuide ›
GeorgiaNot required
None
Not required
None
Cities and counties may add their ownGuide ›
HawaiiOnly in some cases
At least $5,000 when the board requires one
Only in some cases
At least $5,000 when the board requires one
Cities and counties may add their ownGuide ›
IdahoNot required
None
Not required
None
Cities and counties may add their ownGuide ›
IllinoisSet locally
Set by cities and counties
Set locally
Set by cities and counties
Cities and counties may add their ownGuide ›
IndianaSet locally
Set by cities and counties
Set locally
Set by cities and counties
Cities and counties may add their ownGuide ›
IowaOnly in some cases
$25,000
Not required
None
Cities and counties may add their ownGuide ›
KansasSet locally
Set by cities and counties
Set locally
Set by cities and counties
Cities and counties may add their ownGuide ›
KentuckySet locally
Set by cities and counties
Not required
None
Cities and counties may add their ownGuide ›
LouisianaNot required
None
Not required
None
Cities and counties may add their ownGuide ›
MaineSet locally
Set by cities and counties
Not required
None
Cities and counties may add their ownGuide ›
MarylandSet locally
Set by cities and counties
Not required
None
Cities and counties may add their ownGuide ›
MassachusettsSet locally
Set by cities and counties
Not required
None
Cities and counties may add their ownGuide ›
MichiganSet locally
Set by cities and counties
Not required
None
Cities and counties may add their ownGuide ›
MinnesotaSet locally
Set by cities and counties
Required
$25,000
Cities and counties may add their ownGuide ›
MississippiNot required
None
Not required
None
Cities and counties may add their ownGuide ›
MissouriSet locally
Set by cities and counties
Set locally
Set by cities and counties
Cities and counties may add their ownGuide ›
MontanaNot required
None
Not required
None
Cities and counties may add their ownGuide ›
NebraskaNot required
None
Not required
None
Cities and counties may add their ownGuide ›
NevadaRequired
$1,000 to $500,000, set by the board
Required
$1,000 to $500,000 (same NSCB license bond)
Cities and counties may add their ownGuide ›
New HampshireSet locally
Set by cities and counties
Not required
None
Cities and counties may add their ownGuide ›
New JerseySet locally
Set by cities and counties
Required
Confirm with the board
Cities and counties may add their ownGuide ›
New MexicoRequired
$10,000
Required
$10,000 (same CID license bond)
Cities and counties may add their ownGuide ›
New YorkSet locally
Set by cities and counties
Set locally
Set by cities and counties
Cities and counties may add their ownGuide ›
North CarolinaNot required
None
Not required
None
Cities and counties may add their ownGuide ›
North DakotaNot required
None
Not required
None
Cities and counties may add their ownGuide ›
OhioSet locally
Set by cities and counties
Not required
None
Cities and counties may add their ownGuide ›
OklahomaSet locally
Set by cities and counties
Required
$5,000
Cities and counties may add their ownGuide ›
OregonRequired
$80,000 commercial general level 1; $25,000 level 2
Required
$25,000 to $55,000 through your CCB commercial specialty endorsement
Cities and counties may add their ownGuide ›
PennsylvaniaSet locally
Set by cities and counties
Set locally
Set by cities and counties
Cities and counties may add their ownGuide ›
Rhode IslandNot required
None
Not required
None
Cities and counties may add their ownGuide ›
South CarolinaOnly in some cases
$20,000 to $350,000 by license group, in place of a financial statement
Only in some cases
From $7,000 (Group 1 mechanical), in place of a financial statement
Cities and counties may add their ownGuide ›
South DakotaSet locally
Set by cities and counties
Required
$10,000 undertaking
Cities and counties may add their ownGuide ›
TennesseeOnly in some cases
Confirm with the board
Only in some cases
Confirm with the board
Cities and counties may add their ownGuide ›
TexasSet locally
Set by cities and counties
Not required
None
Cities and counties may add their ownGuide ›
UtahOnly in some cases
Confirm with the board
Only in some cases
Confirm with the board
Cities and counties may add their ownGuide ›
VermontSet locally
Set by cities and counties
Not required
None
Cities and counties may add their ownGuide ›
VirginiaNot required
None
Not required
None
Cities and counties may add their ownGuide ›
WashingtonRequired
$30,000 general contractor; $15,000 specialty contractor
Required
$4,000 electrical contractor bond
Cities and counties may add their ownGuide ›
West VirginiaOnly in some cases
Confirm with the board
Only in some cases
Confirm with the board
Cities and counties may add their ownGuide ›
WisconsinSet locally
Set by cities and counties
Not required
None
Cities and counties may add their ownGuide ›
WyomingSet locally
Set by cities and counties
Not required
None
Cities and counties may add their ownGuide ›

Bid, performance and payment bonds for utility work

License bonds are small and required to hold the license. Contract bonds are the ones that decide which jobs you can take. A bid bond backs your price when you bid. A performance bond promises the owner the job gets finished, and a payment bond promises your subs and suppliers get paid. Public owners require performance and payment bonds on most larger jobs, and many utilities and prime contractors ask for them on line, underground and storm work.

How bonding capacity grows

A surety sets how much work it will bond for you, one job at a time and in total. It grows with your financial statements, working capital, track record and backlog. Clean, CPA prepared financials and a relationship with one surety agent are the fastest way to raise it. Read TAKKEL Insurance's guides on how new contractors get bonded and bonding capacity.

How to get bonded

A surety company checks three things before it writes a license bond: your personal and business credit, your financial statements on larger bonds, and your experience in the trade. Most license bonds under $25,000 are written on credit alone, often the same day. Owners of the business usually sign a personal indemnity agreement, which means you repay the surety if it pays a claim.

Common questions

Which states require a contractor license bond?
11 states and DC require a license bond for a contractor or electrical contractor license, including Alaska, Arizona, California, Minnesota, Nevada, New Mexico, Oklahoma, Oregon, South Dakota and Washington. Others, like Florida, Hawaii, South Carolina and Utah, require one only in some cases.
Is a license bond the same as a performance bond?
No. A license bond is required to hold the license and protects the state and the public. Bid, performance and payment bonds are set by each contract, and utilities and public owners often require them on larger jobs.
How much does a contractor license bond cost?
You pay a yearly premium, usually a small percentage of the bond amount, set mostly by your credit. You don't pay the full bond amount.

Summarized from each state's licensing statute, rules and board pages, linked on each state's bond page. This is research to plan from, not legal advice. Confirm with the board before you bid.

Report an error on this page