Colorado Electrical License Reciprocity

Reviewed by Michael Schaeffer · Last verified November 18, 2026

Verified against the Colorado licensing board's own site, November 2026 · All states

Reciprocity agreementsColorado's State Electrical Board accepts journeyman licenses by reciprocity from Alaska, Arkansas, Idaho, Iowa, Minnesota, Montana, Nebraska, New Hampshire, New Mexico, North Dakota, Oklahoma, South Dakota, Utah and Wyoming. Master electricians from other states apply by endorsement. Colorado electrical contractors register with the board and need a Colorado master electrician.

Out of state licenses Colorado accepts

Master or contractor level
None listed
Journeyman level
Alaska, Arkansas, Idaho, Iowa, Minnesota, Montana, Nebraska, New Hampshire, New Mexico, North Dakota, Oklahoma, South Dakota, Utah, Wyoming

Where a Colorado license is accepted

These are the boards whose own published lists include Colorado. Each board sets its own conditions, so check the state's page before you apply.

Master or contractor level
Louisiana
Journeyman level
Alaska, Arkansas, Idaho, Iowa, Minnesota, Montana, Nebraska, New Hampshire, New Mexico, North Dakota, Oklahoma, South Dakota, Wyoming

How reciprocity works

Reciprocity lets an electrician or electrical contractor licensed in one state get a license in another without retaking the trade exam. It is set by written agreements between state boards, and each board publishes its own list, so the list that counts is the one kept by the state where you want to work. Most agreements cover individual journeyman and master electricians, not the company: the business still registers, carries insurance and names a qualifier in each state.

For line contractors, check first whether you need an electrical license at all: many states exempt work on the utility's own system, so reciprocity matters most for customer side work, substations and qualifiers. Our state guides cover that utility exemption. Colorado utility contractor licensing

How to apply in Colorado

Electrical Contractor initial registration via DPO Online Services; requires a licensed master electrician

Official Colorado licensing boards

TAKKEL Insurance SponsoredLicensed in Colorado? Get your insurance in place
Workers' comp, general liability, fleet, equipment and umbrella for distribution, transmission, underground and fiber contractors.
Start a quote ›

Common questions

Does Colorado have electrical license reciprocity?
Reciprocity agreements. Colorado's State Electrical Board accepts journeyman licenses by reciprocity from Alaska, Arkansas, Idaho, Iowa, Minnesota, Montana, Nebraska, New Hampshire, New Mexico, North Dakota, Oklahoma, South Dakota, Utah and Wyoming. Master electricians from other states apply by endorsement. Colorado electrical contractors register with the board and need a Colorado master electrician.
Which states accept a Colorado electrical license?
At the master or contractor level, Colorado electrical licenses are accepted by Louisiana. At the journeyman level, Colorado licenses are accepted by Alaska, Arkansas, Idaho, Iowa, Minnesota, Montana, Nebraska, New Hampshire, New Mexico, North Dakota, Oklahoma, South Dakota, Wyoming.
Does reciprocity let my company work in Colorado?
Usually not by itself. Reciprocity licenses an individual electrician or qualifier; the business still has to register or license in the state, carry the required insurance and name a licensed qualifier.